You are the owner of this article.
breakingfeatured
LAKE DECATUR

So much sediment, nowhere to put it: Lake Decatur dredging delayed by problem at storage site

  • 0
  • 2 min to read
Subscribe for 33¢ / day
dredging1

Crews were at work Wednesday east of Lake Decatur, where berms are being fortified to make room for all the dredged sediment.

DECATUR — Crews dredging sediment from Lake Decatur have been waiting to get to work since April after engineers encountered a problem with the project: The basin where sediment is being stored has reached maximum capacity earlier than expected.

The engineering contractors for the project, Chastain & Associates, felt the sediment "would settle more than it did or what have you, but it just did not and we needed more room in the sediment basin," said Matt Newell, the city's public works director.

The storage site, a 523-acre basin off Angle Crossing Road on the city's northeast side, was expected to hold all of the sediment that crews have been pumping out of the bottom of Lake Decatur since the work began in fall 2014. Crews from Terra Contracting Services worked from February 2014 to August 2016 to raise the berms by 10 feet — but that turned out not to be enough.

+3 
Sediment Basin

The barriers at the sediment basin just east of Lake Decatur are being raised four feet, according to city officials.

Earth-moving crews are now at work fortifying the berms that wall in the sediment, essentially raising the height by about four feet, Newell said.

Newell said the city expects for the dredge to be back up and running sometime in June and it should not affect the project's schedule to finish all work by next year.

+3 
dredging2

The dredge barge sits parked in Lake Decatur near the intersection of Country Club Road and 44th Street in March. Crews can't start work until the capacity of the sediment storage site is increased.

But it could affect the chances for the dredging to finish early and under budget, as it was on pace to do last year.

The total goal of the project is to remove 10.7 million cubic yards of material from the lake. One cubic yard equals about 200 gallons of material.

It's unclear exactly why the sediment is taking up more space than previously calculated. Kevin Myers, a managing principal engineer at Chastain who is overseeing the project, could not be reached for comment Wednesday.


Want to know the latest breaking news right when it happens?

Our Breaking News email is for you. Receive breaking news as soon as we publish it directly in your inbox.

Sign up now:   

I understand and agree that registration on or use of this site constitutes agreement to its user agreement and privacy policy.


Soil runoff is a persistent problem for Lake Decatur, the source of water for Decatur residents and large industrial employers like Archer Daniels Midland Co., due to the substantial agricultural land in the lake's watershed. A lot of topsoil from those nearby farms is washed away by rain events and ultimately settles at the bottom of Lake Decatur.

City officials are in talks with Chastain & Associates concerning the costs associated with the delay. Workers with the Great Lakes Dredge and Dock, which is handling the dredging of the lake bottom, are waiting to get back to work.

"When the contractor's idle, and he's got all of his people and they're ready to work, there's usually a cost associated with that," Newell said. 

On Monday, Decatur City Council members approved the fourth and final bond issue related to the dredging project for $29 million. City officials will be paying up to $2.7 million a year in debt payments until 2038 to cover the cost.

+3 
Sediment Basin

Crews are working on raising sediment basin barriers by four feet east of Lake Decatur.

The bond will also cover the construction of the new Fire Stations No. 1, 3 and 7 at the Decatur Airport. The proceeds will also repay a loan from Busey Bank that was used to pay for the renovations of three existing fire stations.

Councilman David Horn noted at Monday's meeting that including interest costs to finance the 20-year bonds puts the real cost of dredging at more than $140 million, more than the $91 million cost of the immediate project.


Contact Tom Lisi at (217) 421-6949. Follow him on Twitter: @tommylisi

0
0
0
0
0

Decatur Reporter

Decatur reporter for the Herald & Review.

Load comments